PTCL’s Africa1 Submarine Cable Project Set for Completion Next Year, Investment Reaches 75 pc

The company is set to organize the groundbreaking celebration for joining the high-capacity, Africa- 1 Submarine Cable today (February 22, 2025) at Seaview Karachi.

The notice reads: In November 2020, the Board of Directors approved an investment of US$ 59.5 million for the Africa1 submarine cable project. This initiative aims to provide connectivity between the UAE, Europe, and Africa, along with multiple landing stations.

The Company began investing in the project annually as part of its CAPEX starting in 2021. Till 2025, approximately 75% of the total investment has been completed over four years, with the expectation that the full or maximum project cost will be reached within the year.

The project is expected to achieve its Ready for Service (RFS) in Q1 2026. Once the RFS is completed, the Africa-1 submarine cable will be fully operational, and the Company will begin generating revenue from the project, contributing positively to its top-line growth.

The groundbreaking celebration for joining the high-capacity, Africa- 1 Submarine Cable is scheduled

for February 22, 2025, making its landfall at Pakistan Telecommunication Company Limited (PTCL)

landing site at Sea View, Karachi marking a transformative step in enhancing Pakistan’s digital connectivity.