PAKISTAN
Chairman Water and Power Development Authority (WAPDA) Lt. Gen. (Retd.) Muhammad Saeed paid a detailed visit to major components of the Tarbela 5th Extension Hydropower Project (T5 HPP), which is being constructed on Tunnel No. 5 of Tarbela Dam.
The World Bank and the Asian Infrastructure Investment Bank (AIIB) are providing financial assistance for the project.
Member (Water) Syed Ali Akhtar Shah, Member (Power) Muhammad Arfan Miana, General Manager/Project Director T5 HPP, General Manager Tarbela Dam, General Manager (Power) Tarbela, Advisor Projects WAPDA, and Advisor T4 & T5 were also present on the occasion, a WAPDA spokesperson told the media.
The chairman was briefed on the progress, challenges, and timelines for the completion of key activities, including the intake structure, connecting tunnel, powerhouse, switchyard, and transmission line. Overall progress on the project has reached 56 percent. With the completion of civil and electro-mechanical works, the first unit of the project is expected to start power generation in April 2027.
Reviewing the project’s progress, the chairman said that construction work must be accelerated on critical fronts, particularly the connecting tunnel and powerhouse, through coordinated efforts by consultants, contractors, and WAPDA’s project team. He also directed the project management to ensure strict adherence to quality standards stipulated for the project’s implementation.
The Tarbela 5th Extension Hydropower Project has a cumulative generation capacity of 1,530 megawatts, comprising three generating units of 510 MW each. The World Bank and AIIB are providing US$390 million and US$300 million, respectively, for the construction of the project. Upon completion, the project will supply 1.466 billion units of low-cost, clean, and green electricity to the national grid annually. The project will increase Tarbela Dam’s installed power generation capacity from 4,888 MW to 6,418 MW.
Later, the chairman also visited the low-level outlets and powerhouse of the 1,410 MW Tarbela 4th Extension Hydropower Project. Since its commissioning in 2018, the Tarbela 4th Extension has contributed 33 billion units of electricity to the national grid. – LAHORE: APP/ER News Desk
READ MORE
Zong Launches 5G Home Broadband Service in Pakistan
Zong has launched Z HomeFi, a 5G fixed wireless access (FWA) home broadband service, aiming…
BYD Eyes Ultra-Fast EV Charging Technology for Pakistan
Chinese electric vehicle (EV) manufacturer BYD is in discussions with its Pakistani partner, Mega Motor…
Game-Based Digital Therapies Show Mixed Results in Treating Children with ADHD
Stimulant medications are among the most common treatments for children with attention-deficit/hyperactivity disorder (ADHD), helping…
Henri Kagan and Kenso Soai Awarded 2026 Nobel Prize in Chemistry
Scientists Henri Kagan and Kenso Soai have been awarded the 2026 Nobel Prize in Chemistry…
In Memory of Mohammad Akram Sheikh Chairman United Wire Industries
Mohammad Akram Sheikh Chairman United Wire Industries With profound sorrow, we remember Mr. Mohammad Akram…
IEEE Education Society Karachi Section Hosts Dr. Chi-Un Lei Webinar
Rethinking Graduate Education in Age of AI Chair IEEE Education Society, Karachi Section, Prof Dr…